Stage I – Quay from east side of Michigan to east side of Merchant.            April 1 thru May 31, 2019

Stage 2 – intersection of Michigan and Quay                                                      June 2019

Stage 3 – Michigan from south of Grand River to south of McMorran          July and August 2019

Stage 4 – Quay from Huron to Michigan and Merchant north of Quay          August and September 2019

Stage 5  - Michigan from north of Quay to south of Grand River                     September and October 2019

Stage 6 – top coarse of asphalt on entire project                                               May 2020

 Note:

Traffic light at Grand River and Michigan will become a 4 way stop.

The east Quay lot can always be accessible via Fort Street.

Trying to work with the county to get the parking lot on the NE corner of Merchant and Quay access for businesses for parking.

THERE WILL BE NO WORK BOAT WEEK

 